Introduction to DG Queue Velocity
Seeing how many megawatts are queued on a feeder tells you how much is in line ahead of a Site. It does not tell you whether any of it is moving. DG Queue Velocity reads every version of the utility's queue that Paces has kept and shows which projects ahead advanced, stalled, or left the published queue, and how much of the utility's published capacity they take up.
Use it when you're deciding whether to file, wait, or walk away from a Site before committing more spend.
Where DG Queue Velocity is available
DG Queue Velocity runs on Sites served by utilities that publish a project-level queue:
Utility | Queue history in Paces starts from |
ComEd | January 2025 (weekly) |
NYSEG/RG&E | March 2025 |
Con Edison | March 2025 |
Xcel Energy (Minnesota) | March 2025 |
Ameren Illinois | May 2026 |
Reach out to your Customer Success Manager or support@paces.com if you're interested in other utilities.
Requesting DG Queue Velocity
DG Queue Velocity is requested like any other report module and costs 3 credits per Site. For a refresher on requesting reports and tracking credits, see How to Request Reports and Credits.
Open the Site Detail Page and select Request Service, or open the project's Project Hub in Pipeline.
Note: Requesting from a Site automatically promotes it to a project in Pipeline.
In the Power section, add DG Queue Velocity to your request.
Enter the project details and POI for interconnection.
Optionally, enter your project size in MW. Adding it unlocks a capacity fit and a comparison with similar-size projects in the queue.
Submit your request to the Paces team.
Each module is reviewed by the Paces team and delivered within a few business days. You'll receive an email when it's ready, and you can open it from Reports or the project in Pipeline.
Reading the module
Every supported utility returns the same module. What fills each section depends on what that utility publishes.
Overview and rating
A short summary, key facts, and recommended next steps, with a red, yellow, or green rating. The rating weighs how much of the utility's published capacity is already taken by connected and queued projects, and whether the projects ahead are advancing, stalled, or leaving the queue.
Methodology
States which utility queue and line the module used, the latest queue publication date, and the date the utility last refreshed its hosting capacity.
Queue Activity
Projects ahead on the line, with size, status, and how long each has held its current status.
The review level queue, with the utility's published capacity figures shown under the utility's own label.
Twelve months of advances, departures ("left the published queue"), and new entrants.
Stage durations, shown as a median only when enough projects and history exist. Otherwise the module lists the observed values and how many projects they're based on.
A map image showing the line used relative to your Site.
Next steps
To track your request and credits, see How to Request Reports and Credits.